St Helens Crematorium

Project Details

Value: £600,000.00
Design & Build: Yes

Electrical Scope of works summary

– Full upgrade of the LV distribution system with the addition of a Standby Generator including UPS and change over switch, to feed the entire facility.
– Small Power and Programable lighting throughout
– Fire alarm and disabled refuge
– Security, inc. access control, CCTV, Intrude alarm and intercom
– Full Fibre IT infrastructure
– Audio Visual Installation

Mechanical Scope of works summary

– Plant Room Replacement
– Gas Systems
– Steel LTHW Replacement throughout including Trench Heating, Fan Coil Units and LST’s
– HWS and CWS
– Sanitary
– Ventilation
– Air Conditioning
– BMS
– Insulation

Barlows UK were appointed to upgrade the MEP infrastructure of the facility whilst maintaining a live environment. Logistically very challenging which included detailed phasing, enabling and out of hours working. With the facility being the busiest of its type in the north west, it was never an option to close its doors during the build program.
Our team worked with our Client and the end user, St Helens local council, to ensure the smooth day to day running of the facility from start to finish, ensuring the facility was open and ready for business each day throughout the refurbishment.

Project Gallery

Talk to us about your project












    I have read and agree to the website terms and conditions

    Your personal data will be used to process your order, support your experience throughout this website, and for other purposes described in our privacy policy.

    Testimonials

    MUSE Developments


    Alan McBride - Contracts Administrator

    Barlows were the MEP services subcontractor on the recently completed Holiday Inn Hotel in Blackpool town centre.
    We enjoyed working with Barlows and found them to be collaborative, proactive and professional in their approach and they demonstrated experience and knowledge with respect to undertaking hotel MEP services works.
    Barlows have also been responsive, attentive and professional when responding to defects that have occurred during the twelve month defects liability period.